Hello PP Gurus,
Is there a way to create new Distribution key which split the quantity base on daily capacity according to the routing/work center?
Imagine the following scenario: I have a production order of 100.000 PC. My daily capacity is to produce 40.000 PC
So based on the scheduling calculation it would take 3 days to fulfill my order.
Using the GLEI distribution key the system is basically dividing 100.000 by 3 and splitting on MD04, as you see on sample below:
16.04.2019 PrdOrd 000100001503/ZP01/Re Qty: 33.334
17.04.2019 PrdOrd 000100001503/ZP01/Re Qty: 33.333
18.04.2019 PrdOrd 000100001503/ZP01/Re Qty: 33.333
The idea would be to have the quantity split based on the daily capacity, as result we would have:
Day 1: 40.000
Day 2: 40.000
Day 3: 20.000
Is there a way to achieve that? May be different method rather than Distribution Key?
Kind Regards,
HS
Hello,
Distribution key only be used to divide the quantity of the order. Incase , if you want to consider the capacity as , then pls use "capacity planning and capacity leveling" process available in the Std.SAP.
While running a MRP, please consider "lead time scheduling and capacity planning".
Thank you - Kumar Semmalai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.