I have below query related to Work center capacity Planning detail tab.
There are 3 check box in Work center capacity Planning detail tab
1. Relevant to finite scheduling
2. Can be used by several operation
3. Long Term Planning
Also a field "overload" in %
What are the usage & impact of these check box for PM & PP business process.
Hello,
Please read the F1 help of these fields, you will come to know the usage and impact too
Capacity relevant to finite scheduling
You use this indicator to specify that the system should take the available capacity and the load of this capacity into account during finite scheduling.
Several operations can use capacity
You use this indicator to specify that several operations may use the available capacity of this capacity category.
Long-term planning takes capacity into account Indicates that this capacity is taken into account at the time of long-term planning.
Overload
Entry you use to control the percentage by which the load may exceed available capacity.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.