Copy backup process for SAP HANA DB having SAP IQ as cold store

0 Kudos

Hi ,

Please consider below scenario.

1> QA System : HANA DB ( SID : QAH ) , SAP IQ as cold store . ( SID : QAI )

2> PRD System : HANA DB ( SID : PRH ) , SAP IQ as cold store ( SID : PRI)

When we do copyback from production ( PRH ) to Quality ( QAH ), how should we handle cold store ?

Do we need to do copyback for code store too ? If yes, what post steps we need to follow from SAP IQ ?

Best Regards,

Tushar

RolandKramer
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello tushar.chavan01

you have to copy the "Cold Store as well.

you find details about the process in the Document - SAP First Guidance – SAP NLS Solution with SAP IQ 16.x

Best Regards Roland