Should the "Standard Cost Estimate" found in MM03 be equal to the "Val.in rep.cur.", "Val/COArea Crcy", or "Value TranCurr" found in KSB1 (if these values are divided by the "Yield to conf" to get the unit value)?
Hi,
MM03 cost estimate is base structure to calculate the costs of material. Cost estimate considers the cost elements and generates the price at the header level material including substructures (Production + Purchasing + Othe costs).
KSB1 actual line items for orders updated actual cost posting at a cost element level.
Value perspective it updates based on transaction posting currency (production order created and it updates the same vale from CK13N, CO03 (cost analysis), KSB1).
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.