Hello Experts,
We have ETO Scenario( Assembly Processing ) in where Auto Project created by Sales Order.
Whenever I'm creating Sales Order and Enter the Quantity >>> Confirmed Quantity is 0.
But, When Scheduling is carried out ( Network Assignment Performed ) >> confirmed Quantity is increased to Order Quantity without having Stock. How ?
Configuration Setting as below :
1. OVZ9
2. OVZG
3. CP
Material Master Data : Same Availability Control ( 01 ) is maintained in sales view. MRP type in PD.
Expert Pl. Advise.