SAP MRP - Schedule lines

0 Kudos

Hi Team,

I have a material, having 7000 in stock .

MRP type is PD. MD04 is showing there are dependent requirements.

The required stock is far less than available stock for a complete year, still system generates schedule lines and sending releases to vendor. This is happening for single material. kindly assist.

Let me know if more info required.

Thanks

Accepted Solutions (0)

Answers (4)

Answers (4)

Lakshmipathi
Active Contributor
This is happening for single material

In that case, you need to compare MRP views of that material along with other material which you feel is correct. This is the simplest way of identifying the issue

0 Kudos

Hello Lakshmipathi,

Thanks for response.

I did compared materials, but haven't found any diffrence.

Regards,

Indrajit

Prasath
Contributor
0 Kudos

Hello Zope,

In MD04 screenshot (1 & 2) I could not find any schedule line.Only Dep requirement is displayed.

0 Kudos

Hello Prasath,

Thanks for feedback.

yes thats an issue. There are no schedule lines.
However ME38 shows schedule lines for next one year, and system is not allowing to delete those manually. This is causing to trigger releases for vendor.

Do you suspect if there is an issue with table EKET update?

Regards,

Indrajit

Prasath
Contributor
0 Kudos

Dear Sir,

Please check Schedule agreement Validity date and Check if any source list exist for those item. Try with Single item single level MRP in MD03.

Regards,

Prasath E

Prasath
Contributor
0 Kudos

Dear Zope,

Please check the validity of any source list or Quota arrangement exist.

Regards,

Prasath E

Prasath
Contributor
0 Kudos

Hello Zope,

Can you please share the MD04 screen shot for better understanding.

Regards,

Prasath

0 Kudos

md04-1.jpgmd04-2.jpg

Hello

Please find attached.

Regards,

Indrajit

vijay2006ece
Contributor
0 Kudos

Hi Indrajit,
Please verify 'Safety Stock' and 'Min Safety Stock' in Material master MRP 2 view and compare with other materials for better understanding.

0 Kudos

Hi Sir,

My safety stock is 310 which is very less.

Based on current stock situation,all dependent requirements can be covered for a year. Still system is sending releases to vendor with quantity 200 based on minimum lot size.

Regards,

Indrajit