Collective availability check issue in MDVP

0 Kudos

Dear all,

Iam getting an issue while doing a collective availability check for planned orders in mdvp.

1)Components having stock also showing in a missing parts list.

2) If a component has a shortage, the indicator (Availability confirm) is still showing a green colour.

I tried with availability check 01 & 02 in material master, Configuration also i checked against PP checking rule but still no result.

In MD12, when I tried to do the availability check (COMP.ATP) manually also its not working (Availability check window (which I am getting in another client) also not opening.

Please guide me on this issue & do the needful.

Regards

Viswa

Accepted Solutions (0)

Answers (1)

Answers (1)

Mahendran8888
Contributor
0 Kudos

Material or available stock will be allocated already to the previous or earlier order. to your question 1)Components having stock also showing in a missing parts list.