In the Customizing for production orders, you can store a reduction strategy for operations in the order type-dependent parameters (Transaction OPL8). The system then copies these into the operations of an order of this order type. Also check the OPU3 parameter for reduction level.
To reduce the queue time, move time you need to maintain the setting in transaction OPJS.
You can maintain some queue time for operation and then check the scheduling of order.
Best Regards,
R.Brahmankar