Project system component Material valuation_network costing

0 Kudos

Hi,

For our commercial project we use RA based on POC which is Planned cost till date/overall planned cost.

We plan labor and material(stock) on the project. In the costing variant of network planned cost, the material valuation is based one 1. Standard price 2. Moving average price.

The project duration are more than year and sometimes there is price update for these material components.

The problem is that when we re-cost the project the planned price of the component is updated with the latest price even if the requirement date was in past. This changes the POC and also impacts the revenue in current period.

Is there any way the material component can be valuated based on the requirement date and picks the standard price from past instead of the new current price?