Hi All,
As we define MRP area for Subcontractor, if we have multiple subcon vendors we will have to create multiple MRP areas and assign each of them in material master and everytime we have a new Subcon vendor we need to configure a new MRP area.
Please help me understand if there is any way possible to create 1 MRP area for multiple vendors and see the Stock biffurcation in MBLB or any other way to track the stock at vendor location.
Thanks,
Pruthvee
Hi,
It is not possible to use one MRP area (subcontractor) for multiple vendors.
Please refer to the below blog to understand the MRP area for subcontracting process in S/4HANA.
https://blogs.sap.com/2019/03/19/s4hana-subcontracting-with-mrp-area/
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You can only have one sub-contractor vendor assigned to one MRP area. Multiple vendors cannot be grouped together in a single MRP area as per standard SAP system design.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.