cancel
Showing results for 
Search instead for 
Did you mean: 

Incorrect FF-relationship between activities

former_member308518
Participant
0 Kudos

Hello,

Between network activities I’m using the relationship type FF
(i.e. the successor should not end earlier than the predecessor).
However, in my project the successor ends on earlier date - 26.03.2019, than the predecessor on 27.03.2019.

These activities are automatically scheduled for the same point in time as follows:
predecessor - latest finish on March 27, 2019 at 00:00 hours
successor - latest finish on March 26, 2019 at 24:00 hours

Do you know how to set up the system so that the predecessor uses 26.03.2019 24:00 instead of 27.03.2019 00:00 during scheduling?

I will appreciate your help very much.

With best regards,
Robert

Accepted Solutions (0)

Answers (0)