Hello,
Between network activities I’m using the relationship type FF
(i.e. the successor should not end earlier than the predecessor).
However, in my project the successor ends on earlier date - 26.03.2019, than the predecessor on 27.03.2019.
These activities are automatically scheduled for the same point in time as follows:
predecessor - latest finish on March 27, 2019 at 00:00 hours
successor - latest finish on March 26, 2019 at 24:00 hours
Do you know how to set up the system so that the predecessor uses 26.03.2019 24:00 instead of 27.03.2019 00:00 during scheduling?
I will appreciate your help very much.
With best regards,
Robert