Hi
I want to activate Preventive maintenance operation under of the condition of number of producted part
For example, an injection mold need to have a preventive maintenance each time 50.000 cycles have been done.
How can I implement this in SAP ?
Thanks in advance
Best regards
Daniel
Hello,
You can create the PRT as equipment and then assign this to the routing operation in production.
In equipment master create a measuring point and in PRT tab of equipment master enter a maintenance plan and the measuring point. When you will confirm yours production order a measuring document will be created and will keep updating that counter.
Please refer this useful documents on same topic,
http://scn.sap.com/docs/DOC-70543
Performance based planning for the PRT' S used in routing
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.