PO should not be created in Easy Cost Planning without a PR.

0 Kudos

Hi,

We are using Execution services in Easy Cost Planning in S/4HANA, for the creation of PR and PO for projects. However, according to the requirement, PO should not be created without a PR. Would adding a validation at PO level help? If yes, I want to know how it can be done, or is there any other way to achieve this.

Thanks.

ivy_li
Active Contributor
0 Kudos

Hi,

I adjust the tag since it is irrelevant to SRM PO.

BR,

Ivy

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

You can use BADI ME_PROCESS_PO_CUST for adding check logic and issue a custom message to prevent PO without PR.

Please refer SAP consulting note 1884517 - Cannot use document type to make requisition mandatory in PO

664424 - Requisition number not mandatory in ME21N

Best Regards,

R.Brahmankar