on 03-18-2019 1:59 PM
i have a requirement of strict operation restriction for Qm.
example i have
operation 1 welding pp01 control key
operation 2 inspection for welding
operation 3 cutting
operation 4 inspection for cutting
now the requirement is if i inspect in operation 2 if it is failed it must not allow me to record result for operation 3 .
how this ca be done in standard settings??
2.i have explored the make settings for operation completion in spro result recording.
i dont find any use regarding this purpose
3. if i done this reject operation 2 . against that rework of welding has to be done ?
how this can be achived?