MD04 - Cannot find panned order and convert to PR in S/4HANA 1809

Greeting,

I have tested MD04 in IDES for safety stock, when the stock level is under safety stock we maintained in material master, system will show a planned order and we can convert it to PR or PO.

However, I tested this scenario in my current system, I cannot find planned order in MD04

I am testing if the stock level is under safety stock maintained in material master, not to mention converting to PR or PO.md04.png

This is my 1st time to config MRP, therefore, I don't know how to start it, I also read a lot of discussions from internet, but no idea how to reach it, is there any experts willing to teach me?

Thanks & Best Regards

Roger

md04.png (37.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Mar 16 at 08:03 AM

    Hi Roger,

    You can find a lot of forums about MRP configuration, check the important configuration parameters.

    1. Activate MRP for Plant

    2. Plant Parameters for MRP (SPRO)

    3. Carry out overall maintenance for MRP group

    4. Number Ranges for Planning

    5. MRP type (Optional)

    6. MRP controller

    7. Procurement Type

    8. Special Procurement Type (optional)

    9. Lot Sizing Procedure

    10. Scheduling Margin Key

    11. Scheduling Parameters for planned orders

    12. Maintain Planning calendar

    13.Define Order type for Conversion

    14.Define Planning Horizon

    After configuration settings completed create the planning file entry via MD20 transaction code and run MRP via MD02 or MD03 to generate planned order.

    mrp-configuration.png

    md02.png

    md03.png

    Best Regards,

    Lingaiah