PDT with global outline agreement

hello all

here is our scenario:

1) we created a global contract that can be used by all the company codes of the firm.

2) as the plants are all over the world, we left the PDT empty: If we create a PO directly, it is no problem as in this case the PDT comes from the PIR

the issue is that when the MRP runs, the Preq does not consider the PIR and therefore the release and delivery time are the same.

the only way we found to change this, is if we set the GR time in the material master as if it was PDT and the dates would come correct.

we also plan with APO, but there is no solution that we are aware of from that side.

But it is not an ideal solution; has anyone come across such an issue?