Hi,

Does anyone know what the setting is in SAP to make sure any planned independent requirements in the past are ignored by the system? So that you don't have to manually go into a screen like MD62 and 'tidy up' the old forecast that hasn't been consumed?

Thanks

Adam

Accepted Solutions (0)

Answers (1)

Answers (1)

lingaiahvanam
Active Contributor
0 Kudos

Hi Adam,

You can run reorganization jobs MD74, MD75 and MD76 to delete unconsumed planned independent requirements with ket date (past date).