Re-order point planning scenario

50 Views

I used the Re-order planning with "External" Requirement and it works as desired for the "Finished material"

The ROP 100.

Stock: 110

S.O qty : 20

Net qty= ( 110-20) = 90. (The Cust.order net with the stock)

Since 90< 100 (ROP) it planned 10 nos.(Planned order)

----------------------------------------------------------------

Q: Could we make the "Dependent requirement of component" net with stock and when the net qty < ROP , create a planned order .. (i.e)work the same way as above?