Hi Team,

Please help me to solve it..there is one work center A and under the same work center we have a subsidiary work center B . out put from A will move to B , so when we run WC A ,capacity of WC B also will be consumed ..could you please help how to solve it?

Thanks,

Vijesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member189817
Active Contributor
0 Kudos

Hello

  Why can n't you treat both A and B as one work centre ? Is it any Business Impact ?

Regards,

Velmurugan S

former_member232086
Participant
0 Kudos

Hi,

we can do it when there is 1 to 1 relationship

we have one work center x and the out put of the same will be reprocessed in 5 other work places.

so that 5 work places are sub unit of work center x..how to link the 5 sub units to wok center x?

Regards,

Vijesh

former_member189817
Active Contributor
0 Kudos

Hello

I am not completely understand your requirement but have you tried  sub-operation functionality  in routing?

Regards,

Velmurugan S

Answers (3)

Answers (3)

0 Kudos

Hello,

you could set up a Pooled Capacity through CR12 for the corresponding capacity category (machine, labor,...) and then assign it to both workcenters A and B. Then, each time that you will be consuming capacity for that category from one of the two workcenters, the capacity will be consumed from the other one as well.

Regards,

Jose.

jeremy_peckham
Explorer
0 Kudos

Have you considered using a capacity pool?

former_member232086
Participant
0 Kudos

pls help