Hello Experts

I’m implementing DIP for the usage quotation creation and sales pricing for S4HANA project but I have a problem in transaction dp82 “No expenditure items found” after following the below process:

1- Create project in 'cj20n' and assign activities & resources for the project to make network costing for the project.

2- Assign partner to the project.

3- Assign DIP profile to the project and make the main WBS element as a billing element.

4- Put the project code in the transaction DP82 and the error "No expenditure items found" appear to price my project.

My configuration to DIP profile:

Usage: quotation creation and sales pricing, ZMBQ (sales doc. type).
Characteristics: cost element X X

Material X X

Object number X

Transaction currency X

Unit of measure X

Source: planned cost - total records.

Cost element set (all) which contain all cost element from 0 to zzzzzz

Material determination: material code (210001) and its criteria the set of cost element (all)

Hint: if i make cost planning for the project by cost element transaction (cjr2)

I can access the transaction dp82 with only the cost distributed in cjr2

The system behavior is strange in this version, please help me if you may.