Routing- Time between operations

1284 Views

The requirement in scheduling :

The system should always schedule such that when the component A moves between 2 different operations (Operation A to B) there should be a " Time lag or wait" before it moves to operation "B".

Qty: X

Operation A:

Start Time: 8.00 am

End Time: 8.30 am

Operation B:

Start Time : 9.00 am

End Time : 10.00 am

There is always a "30" mins lag between operation A and B, so operation B starts "30 min" after 8.30 am (i.e) at 9.00 am.

This time varies with "Components".

I am thinking of "Inter operation Times" (Wait Time).

Do you see anything different here and should work in REM also.?