Is it possible to create process order in advance for materials not available until that date? Example I have new material Y coming in on Thursday to replace material X. I want to open process order on Monday to consume material Y. Presently it will consume material X.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Sep 29, 2016 at 01:01 PM

    Hello,

    Could you please elaborate your business requirement? In standard SAP you can create the process order in advance.

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.