PP work centre capacity and operation times

59 Views

Could someone advise how to set up a PP workcentre so that the operation time is calculated taking into account the number of capacity units (heads) assigned to the work center. For example if two people are on a work centre the standard time of 10 hours can be cut to 5 hours as both can work on same operation at the same time and the operation start and finish dates / times are calculated based on this?

Thanks for any input available.