on 09-26-2016 3:17 PM
Hi Experts,
We have updated holiday calendar.
We have done Customization in DEV tested OK Move to quality Tested OK But in PRD
PRD Holiday Calendar is updated with holidays but factory calendar and work schedule not updated generated PT01 in DEV
Please let me know how to solve this issue,
Thanks,
Sadeq Ahmed
Hi Sadeq,
Issue would be basis team might have moved work schedule generation TR to Live first then holiday calendar TR. Always holiday calendar configuration TR to be moved first followed by work schedule generation TR.
Thanks,
Naren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sadeq,
Not sure what the actual problem is, but please consider these points below:
Kind regards,
S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Simone,
For the Reply, The issue is Solved,
Yes before it self i have updated the holiday calendar and save in TR by transport button, and generated Work schedule and save in TR Both Changes has moved to Quality works OK,
Moved to Production initially Work schedule is not updated but after some time its got updated need to contact Basis for why its got delayed.
Thanks,
Sadeq Ahmed