SAP Procurement DOA

Former Member
0 Kudos

Good day,

We have a serious situation with regards to release strategies and how to set-up the different values for PR's and PO's.  We have Z-tables in place and they have been maintained correctly, but for some reason the release defaulted only to two release levels.

I have two examples.  A PR for 2.8m has only two release levels, CC Owner and PRC Manager.  It should route to 4 more release codes.  I know what the problem is.  Table T16FS needs to be maintained, but the system is not modifiable through SM30.  We can open the system via SE06 but nobody is willing to make live changes

Our problem actually is that release procedure are not to be transported among clients.  This means that whenever changes are made through IMG, the system does not give me the option to create an ERDK, which can be transported to UAT for testing, and eventually to ERP

I am in desperate need for a SAP Consultant who's expertise lies in Release Strategies.

Anita

Accepted Solutions (0)

Answers (2)

Answers (2)

Prasoon
Active Contributor
0 Kudos

Hi,

   You mentioned about Z table - which means that there is an enhancement which is altering the standard. So there is limitation for others to suggest the solution, since its your company specific enhancement.

    Its not suggestible to open the PRD client for configuration. You have to do the settings in Dev system and then move to QAS and then in turn to PRD. If the configuration is not creating the TR in Dev, check the SCC4 settings for the particular Dev client.

    Alternatively, you may create manual TR as well, for the release strategy, from the menu, as shown below:

Regards,

AKPT

Christhie
Product and Topic Expert
Product and Topic Expert
0 Kudos

Does this thread help? https://scn.sap.com/thread/1512758