on 09-16-2016 4:30 AM
Hi,
In SMI scenario with replenishment order, is there any way we can match PO number range from ECC system while creating RO in SNC.
I am finding it difficult to match the current number range in ECC with SNC PO (created by RO).
Thanks,
Vaibhav
Hi Vaibhav,
There is no standard way of checking the current PO number range in ECC, while creating a RO in SNC.
Normally we create a separate number range for SMI PO and then create same number range in SNC. This will automatically make sure that both POs number are in sync in ECC & SNC.
Dont use this number range for any other scenario, this will again create same problem of inconsistency.
Regards,
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi vaibhav,
In ECC system ,you can check the below path for RO number range.
spro->Material Management->purchasing->Purchase order->Define Number ranges here you can check the intervals.
From SNC system you can check number ranges in SNRO tcode there you can check the ranges for objects(/SAPAPO/R-//SAPAPO/R+).
Thanks&Regards,
Vishnu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.