Project Planning in Parts Or Time based

former_member261747
Contributor
0 Kudos

Hi

        We created a project through CJ20N and Assign FG Material Qty = 100 MT. Then we run MRP through MD51. Client do not want to create PR of raw material Required for production 100 MT at once. He wants to plan FG in parts. Means Sep 2016 = 40 MT, Nov 2016 =60MT. Please suggest how we can handle this situation.

As per our business we have 30 -40 Material for one  project  & if we edit requirement twice it become 60 fg. we do not want to assign each material  twice.

Please suggest how can we plan as per time period.Like  40 MT in Sep & 60 MT in Nov with out entering requirement multiple times.

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

Hi,

May be you can generate only planned orders from MRP and convert the planned orders to PR as per requirement later.

Thanks

Abdul

former_member261747
Contributor
0 Kudos

Hi Abdul

               I created Planned Order with selection Create purchase Requisition "3"(planned Orders ) in MD51.Then i created two purchase requsition from this single Planned Order With different time and delivery Qty. but while converting this PR To PO then getting exception msg "20". Please suggest why system is not able to convert PR to pld.

PLD >PR>PO, PLD=10 , PR1=5,PR2=5, PO=5 With exception Msg 20

former_member194456
Contributor
0 Kudos

Hello

Exception message 20 means there is no more requirement of the material.

Could you please share the full screen shot of the MD04, as I can see the PRs are still there and PO is not related to these PRs of project.

Regards

SS