on 09-15-2016 10:11 AM
Hi
We created a project through CJ20N and Assign FG Material Qty = 100 MT. Then we run MRP through MD51. Client do not want to create PR of raw material Required for production 100 MT at once. He wants to plan FG in parts. Means Sep 2016 = 40 MT, Nov 2016 =60MT. Please suggest how we can handle this situation.
As per our business we have 30 -40 Material for one project & if we edit requirement twice it become 60 fg. we do not want to assign each material twice.
Please suggest how can we plan as per time period.Like 40 MT in Sep & 60 MT in Nov with out entering requirement multiple times.
Hi,
May be you can generate only planned orders from MRP and convert the planned orders to PR as per requirement later.
Thanks
Abdul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abdul
I created Planned Order with selection Create purchase Requisition "3"(planned Orders ) in MD51.Then i created two purchase requsition from this single Planned Order With different time and delivery Qty. but while converting this PR To PO then getting exception msg "20". Please suggest why system is not able to convert PR to pld.
PLD >PR>PO, PLD=10 , PR1=5,PR2=5, PO=5 With exception Msg 20