on 09-12-2016 5:21 PM
We are discovering in some instances that when creating orders in TLB the orders are being pushed out from the ship date showing on the deployment stock transfers. When creating manually they are correct, when creating through a TLB run the days are being pushed out. Anyone else seeing this? It seems to have started after our upgrade in July. We upgraded to 7.1.
Hi Christopher,
Please check the OSS note 22407779.
at https://launchpad.support.sap.com/#/notes/2240779
Regards
Raj Kakarala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Christopher,
What exactly do you mean by "pushed out"?
Have you noticed if this behavior happens for specific scenarios, or it's a random issue?
Kind regards,
Pablo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.