Skip to Content

Creation of PS Network/Activity for selected cProject element

Dear Experts,

Thanks for helping in creating the WBS element automatically from cProject structure using account integration.

Will it possible to create network and activity in Project System from cProject ?

I have integrated Portfolio Item with cProject and then from cProject to Project System. If there any other way of achieving it then also I am ready to change the config.

Note : My requirement is to create a PS Project (with set of WBS elements and Network Activities) from cProject, so that I can use DFM to perform the scheduling.

Regards,

AP

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 12, 2016 at 01:43 AM

    Hi Anil,

    As per my knowledge, this is a non-standard SAP functionality and you might achieve this by following development + logic.

    Let's say that, in Customizing, PPM Project element creates WBS elements in PS. Now any modification to this mapping has to be done through BADIs. If I am not wrong, you can try BADI DPR_FIN_IMP_FACTORY and Class CL_DPR_FIN_GECCO_IMPLEMENT.

    SAP also provides an example implementation class - DPR_FIN_IMP_GECCO - which explain how you can set accounting integration when replicating project to ECC.

    But the key for you here will be to change the transfer object type from WBS to Network activity for selected components. What I would suggest is to configure a unique "Task type" and use it in operational PPM Project where the PPM element is to be transferred as Activity and not WBS. Now this Task type has to be identified in above mentioned BADI for its conversion to Network activity in ECC / PS Project.

    Please check with your development team reg details of which method to be implemented specifically to achieve the results.

    Best regards,

    Aditya

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.