How to move all orders plus a period of time?

former_member597028
Discoverer
0 Kudos

In PPDDS  I need to move all orders plus a interval of time. For example if the planned order starts at 12 move to 12+t      for every order on a group of resources    i don't want to change the spacings just push all back

Is there any other way than select all and drag and drop with the control key depressed?

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

In DS board /SAPAPO/CDPS0  for your DS strategy define specify date, so while rescheduling system will ask you for a date and time.

Best Regards,

R.Brahmankar