Sudden high requiremnt in MD04

HI

as in attached screen dep requirement are seen more on Mondays...else they are in range for other days....this is semi finish material....its lot size in planning based and planning calendar is Tue....I want to what may be the reason for sudden spike for requirement mostly on Mondays..but for other material with same setting the reuirement are stable as in screenshot 2....what may be the reason for this....

Capture3.PNG (26.8 kB)
Capture2.PNG (16.4 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Sep 08, 2016 at 12:52 PM

    Hello

    It seems that, for the first material, there are uncovered requirements within the time fence, so MRP must create a new replenishment proposal without the time fence, to cover all the requirements. For the second material, there is a replenishment element within the time fence, so it is not necessary to create a new one to cover the requirements.

    Regards

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.