Hi All,
We are using PPDS for planning, and in the planned orders, start date is on a non working day.
On checking the factory calendar which is mapped to the resource are looking fine, where we mentioned 5 days working.
can you please provide your views on this. Thanks in advance.
Regards,
Yasar
Hi Brahmankar and Vinoth,
Thanks for your valuable comments, have changed the shift timing earlier it was till 24:00:00 and we have changed to 23:59:59 and it is fine now.
Thanks,
Yasar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the time stream of Calendars maintained under each planning (Production Plant) location in Location Master, as well.
Just my thoughts
Regards
Vinoth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please check the heuristic Strategy Profile if Non- working time is active.
Refer SAP consulting note 397989 - PP/DS: Scheduling (Documentation)
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.