Hello all

I've got a problem with the after installing a new release 7400.3.9.1125 Build 1681865 , (the old one was 7300.2.4.1083 build 1407322) on the project planing I can't see the WBS, see attached picture

but when i chose the project planing the WBS are not there :

I ve been cheking the options menu and I've excacly the same than I had on the previous version so I suppouse that this is a bug or something has change on the SPRO on the new version affection the project profile SAPPS_TP0001.

Is there any setting to fix that issue ?

Many thanks in advance

Ferran

pastedImage_0.png (48.1 kB)
pastedImage_1.png (66.3 kB)
Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • Posted on Sep 06, 2016 at 07:04 AM
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 26, 2016 at 01:14 PM

    Hello all

    finally I've solve the issue coming back to the version 730 , I've found out that the new 740 is having problems with PS that are not yet solve .

    I'll try to upgrade in the future when new notes for that issue appear from SAP .

    thanks every body that has participated on this discussion

    regards

    Ferran

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 06, 2016 at 01:24 PM

    Same Issue For Me Have you got any solution for it.

    Please Let me know for any solution!!

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 27, 2016 at 01:24 PM

    Hi Ferran,

    We have Updated to GUI 7.4 patch 5 and the issue is solved !!


    Thanks,

    Sadeq Ahmed

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Sadeq,

      Notes 2344974 and 2351702 pertain to this problem. Note 1053737 provides the schedule for delivery of GUI patches 10 and 11 (10 was due last week). Please close the issue if resolved.

      Regards,

      Pratap

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.