on 08-30-2016 11:05 AM
Hi Gurus,
I am using S/4 HANA, I am unable to find the setting of Copying results while doing the Recording of Results in inspetion lot.
I cannot see the Setting "Make settings for Copy of Inspection Results " in SPRO.
Where can I find this setting? or is there any workaround?
Thanks.
Regards,
Max
Hi Max,
Please check the below things
SPRO >> SAP Reference IMG >> Activate Business Functions (SFW5)
in this, check the ENTERPRISE_EXTENSIONS for EA-PLM is activated. Also, check ENTERPRISE_BUSINESS_FUNCTIONS for OPS_QM_EXTENSIONS is activated.
If not activated, then activate these and check the SPRO the node for "Make setting for Copy of Inspection Result" will be added.
Regards,
Dipeshkumar Bhavsar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This might be helpful. Take the clue from following links.
Copy Inspection Results from Previous Inspection Lot - Product Lifecycle Management - SCN Wiki
Copy Inspection Results - Inspection Lot Creation (QM-IM-IL) - SAP Library
SPRO Settings: COPY INSPECTION RESULTS DURING R... | SCN
Regards,
S Ahmed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.