Copying source code from one Dev. Configuration to a new one in SAP NWDI

We are using NWDI for transport management in our project. We have used a development configuration, say FXX to do all our development. The project went live. Now for all our future fixes and support we can't use this configuration as the runtime settings will be different.

We must follow a different transport path for all our future development For this we need to create a new development configuration, e.g FYY in CTS+. The challenge is how to copy all the base codes from FXX to FYY.

Can anyone help me.

Thanks in advance

Nayeem Akhtar

SAP PO consultant

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 09, 2017 at 04:14 PM

    Hi Nayeem,

    I would suggest that take a look at the following wiki page:
    https://wiki.scn.sap.com/wiki/display/Java/Create+and+use+Standard+Development+Configuration+in+CM+Services+7.3

    You can see under the part "Export Service UI" how you can export your codes from the FXX development configuration. There is written also

    how you can import the exported SCA to the new development configuration (FYY).

    I hope I could answer your question.

    Best Regards,
    Szabolcs