Orders not scheduling automatically for Heijunka timetable

Hello Gurus,

I have created the timetables for the Heijunka using /LMPC/FPL2. But the orders are not getting scheduled automatically. What will be the reason?

Thanks and Regards,

Amol Kale

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Aug 23, 2016 at 03:19 PM

    Hello


    If the planned orders were created by MRP, you should set the parameter scheduling = 2 so that they are automatically scheduled.

    BR
    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello Caetano,

      User has created the Heijunka timetable at product level using /LMPC/FPL2. He defines the calendar at week level. Normally does the planning by Heijunka. The planned order dispatching is not happening automatically even if the product is maintained in the timetable for the week.

      Thanks and Regards,

      Amol Kale

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.