Dear All

         I'm  learn the function assembled to another plant。I have test the stand special procurement 80,and set the strategic 40 for FG。I want to achieve the function like that :receive sales order in plant 1000 but product in plant 4000。

but I failed;can anyone give me some document about this function ,maybe some mistake in my configuration at spro 。

please help me

thank you very much!

Accepted Solutions (1)

Accepted Solutions (1)

former_member194456
Contributor
0 Kudos

Hello

Please elaborate what is missing and where you failed

Have you maintained the Alternate production plant in the special procurement key 80

Have a look on the documents

Production in Alternative Plant - Special Planning Processes - SAP Library

http://www.erpgreat.com/production/planning-production-and-alternate-plant.htm

Hope this helps

Regards

SS

Answers (4)

Answers (4)

former_member193808
Active Contributor
0 Kudos

Hi,

Please refer the document;

Thanks

venkatanaresh_yadav
Participant
0 Kudos

Dear,

Share the screen shot of the special procurement key configuration.

You need to follow the below steps

  • Configure the special procurement key as shown in the below screen shot.
  • Assign the special procurement 80 in the material master in plant -1000
  • Create Sales order in plant 1000
  • Run MRP in plant 1000
  • Check the requirements in plant 4000 (MD04) , you should find the planned order in plant 4000

Thanks,

Naresh.

Shubham1
Employee
Employee
0 Kudos

Hi,

Please read this useful thread.

differnece between special procurement type 40 ... | SCN

-Shubham

former_member185450
Active Contributor
0 Kudos

Hello Michael,

First assign the production plant in the special procurement type 80 through SPRO

then assign the same Special procurement type 80 in the planning plant material master then create the demand and run the MRP, after that observe the MRP Results system will generate the proposals in the alternate production plant

Refer the below threads for better understanding

SAP PP - Planning & Production Alternate Plant

Regards,

Venkatesh..