Dear Experts,
I am new to Repetitive Manufacturing scenario and we are planning to implement Heijunka Pattern in Sequencing.
As of Now I understood that standard MRP Process can be a predecessor for Heijunka and created settings as per below
1. material master with
Lot size= FX
Procurement type =E
REM profile= 0005
2. reference Routing Set
3. Production version with Reference Operation Set and Production Line(work Center)
4. MD61: Ind requirements
5. Run the MRP successfully
but unable to See the Planning table for newly created Production Line (please suggest if i am missing anything) (by using existing production line I can see the Planning Table for material)
About Customization I have done following setting
SPRO->Production->REM->Planning->Sequencing -> Planning-> Processing Profile
But here option for "Production Smoothing/leveling (Heijunka)" is not appearing
And in Transaction code LAS2 below Selection Parameters are not appearing
1. Planning Profile
2. Visualization Profile
I have created both profile in Customization.
Thanks & Regards,
Prasad Joshi
Hello,
Please check business function LOG_PP_LMAN is activated in your system.
Refer below links for more details
Heijunka: Settings for the Planning Profile - Sequencing (PP-FLW) - SAP Library
Best Regards,
R.Brahmankar