I have set my material master with parameter :

Forecast every week = 7 Pcs (1 Pc/day)

Planned delivery time = 1 day

Planning cycle every Monday

Delivery cycle every Wednesday

Today august 22 2016 (monday).

When i run MRP, system create purchase requition = 12 Pcs (with delivery date on wednesday august 24 2016).

Can anyone please explain me, why system suggest MRP = 12 Pcs?

Thanks

Yan

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Aug 22, 2016 at 11:14 AM

    Hello,

    Please check the lot size may be it is weekly like WB also check minimum lot size , any rounding value defined in materials master MRP 1 view.

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Brahmankar,

      Thanks a lot for your reply.

      I've got my mistake.

      My planning calendar is 5 days/week. It should be 7 days/week.

      I checked it in WB02. After change this calendar, i get the order quantity that i want.

      Thank You.

      Regards,

      Yan

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.