Hi Expert,
Please help me to understand.
I have set my material master with parameter :
Forecast every week = 7 Pcs (1 Pc/day)
Planned delivery time = 1 day
Planning cycle every Monday
Delivery cycle every Wednesday
Today august 22 2016 (monday).
When i run MRP, system create purchase requition = 12 Pcs (with delivery date on wednesday august 24 2016).
Can anyone please explain me, why system suggest MRP = 12 Pcs?
Thanks
Yan
Hello,
Please check the lot size may be it is weekly like WB also check minimum lot size , any rounding value defined in materials master MRP 1 view.
Best Regards,
R.Brahmankar