Hi all,

I have a problem in preventive maintenance, please provide the solution

I created a maintenance plan, scheduled, as per the schedule call object been triggered(order), i released the order it is having 10 tasks, but in confirmation i confirmed only 9 operations due to some reasons i could't complete one task. i planned to complete the pending task in next schedule.

how the pending task will come to next call object automatically, is there possibility to capture pending tasks in previous schedule and pass to next call object.