Skip to Content

Fore cast based Planning

Hi Friends,

I have changed MRP type as "VV" forecast based planning and consumption of the Independent requirement already happens when the sales order is entered however

is it possible to somewhere put a setting for these ForReq forecasts to also consume already open sales orders, deliveries etc...(begore GI is done)

could you please provide some light on this.

Thanks & Regards,

Srinika.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Aug 18, 2016 at 02:07 PM

    Hi Srinika,

    Check the below link...

    SAP的学习和考试 Learning & Examination: ~ MM-MRP Trading Scenario MRP Type VV

    Hope this helps

    Thanks

    Kumar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 19, 2016 at 06:17 AM

    Good morning.

    From what i know, VV MRP type does not take into consideration sales orders etc. In VV the ForReq requirement is only reduced when a consumption is posted (ie goods issue on delivery, 261 move, etc). So, i am curious on your statement that "I have changed MRP type as "VV" forecast based planning and consumption of the Independent requirement already happens when the sales order is entered" as this is not the standard system behaviour. Can you please share some screenshots?

    In order to achieve what you are looking for, you should switch to another MRP type that considers net requirements planning (ie PD), where, in its customisation you can mark "forecasting" as obligatory (DONOT alter PD, make a copy of it and then change its settings). In this new type, remove the "Forecast requirements relevant to MRP" indicator.

    Run the forecast for your materials. With the previous settings, forecast will not be automatically transferred to demand management. Put in your materials a strategy that allows for PIR reduction (i use 40, but this depends on your business scenario), and in MRP3 screen (or in the MRP group) put backwards and forwards condumption periods in days, so MRP checks in order to reduce the requirements. Finally, transfer the forecasting results to demand management using transaction MD70 and PIR type = VSF.

    Then, after PIRs are transferred to demand management, you will see that when a sales order is entered, the VSF requirement is reduced accordingly. If not, we will have to check if the requirement coming from the sales order matches with the requirement class of the strategy you are using.

    Best regards,

    Nikos

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.