Dear Experts,
Could you please guide me on where I can find (in configuration) this connection, and what are the process steps to establish this connection:
1. Link between the Item and cProjec
2. cproject to PS Project
Is there any document created on that on SCN?
If not, kindly let me know the procedural steps for it.
Best Regards
Saurabh
Dear Saurabh,
detailed information concerning the Link from Portfolio Item to Project Management Project can you find in the online documentation under:
Related Objects Management - SAP Portfolio and Project Management - SAP Library
Wiki:Integration Options (PFM) - Product Lifecycle Management - SCN Wiki
Concerning the Link from Project Management Project to PS Project you have to use the functionality of the accounting integration. Information are available in the online documentation under
Accounting Integration - SAP Portfolio and Project Management - SAP Library
Wiki: Accounting Integration - Product Lifecycle Management - SCN Wiki
Information are also available in the configuration guide in chapter "Defining Settings for Assigning Objects".
Best regards,
Judith
Any pointers on this Please?
Best Regards
Saurabh