I have an issue with finite scheduling of my service orders. I have set-up the work centre capacity flagged for finite scheduling without overload. Capacity set for 3 resources 75% efficiency in daytime shift giving 1620 minutes capacity per day. In customizing tcode OIOI for ordertype and plant on activity release order i have unflagged the no check for capacity availability with overall profile SAPPM_G013 and user decision if capacity is insufficient. In tcode OPU7 flagged automatic scheduling and automatic log. Used scheduling type forwards in time with update of basic dates based on operations. When i check CM01 i have already an overload. When new order is created and released for same week overload is increasing and the dialogue box for finite scheduling is not shown.

My question is now why do i miss the dialogue box and why is finite scheduling not working. Did i miss an important setting if so which one.

Regrads Bram de Waard

Accepted Solutions (1)

Accepted Solutions (1)

dimasluis_defaria
Active Participant
0 Kudos

Hi Bram de Waard,


I think that you are not making the capacity availability for the orders.  If it goes creating orders in the same date will give same overload.  You need to do CRP in the tcodes CM33 or CM34, CM25 or ...


Regards


Dimas Faria.

Former Member
0 Kudos

Can you indicate what i should do in these transactions. I do not want to despatch the operation at this moment. I can only use these transactions as refernece. I prefer the overview of CM01 but then adjusted through the settings to a day view which gives me an insight in my overload per day.

Still strugling with the profiles. This because with the finite scheduling is only active after one week of today. I miss one week of warnings. How can this be solved?

Regards Bram de Waard

dimasluis_defaria
Active Participant
0 Kudos

Hi,

You are not working with finite scheduling.  Because you are not making the dispatching (because you don't make CRP and OIOI this turned off CRP)

CM01 - only capacity evaluation

Where you are seeing:  the dialogues box goes finite scheduling i not shown ?

Please show me yours  screens..

Regards

Dimas Faria

Former Member
0 Kudos

I have the following setting used in OIOI upon release of the order:

The dialogue box is not shown when i create an order within first 7 days when plannend on a day with overload

Is it possible to have automatic despatching?

Regards Bram de Waard

dimasluis_defaria
Active Participant
0 Kudos

Hi,

Ok, OIOI this turned on

OPU7

I made a test, and the system showed the screen even in the date today

In the release, open box bellow

System suggests me the following day, that I have availability

date modified

Check your overall profile (and subprofiles)

Regards

Dimas Faria

Former Member
0 Kudos

I have the same set-up for OPU7. I am struggling with the sub-profiles in the overall profiles. Did you adjust the sub-profiles or kept them as standard delivered. If not which did you adjusted

regards Bram de Waard

dimasluis_defaria
Active Participant
0 Kudos

hi,

All standard

overload = 120 %

Create an order for today with quant hours larger than overload

Regards

Dimas

Former Member
0 Kudos

Is it posible to share a screen shot from the overall profile and sub profiles use for this order

Thanks regards Bram de Waard

dimasluis_defaria
Active Participant
0 Kudos

Hi,

Regards

Dimas Faria

Former Member
0 Kudos

Thanks

Answers (2)

Answers (2)

psr2412
Contributor
0 Kudos

Hi Waard,

When new order is created and released for same week  the dialogue box for finite scheduling is not shown.

You are talking about finite scheduling box in work center,

could you plz. elaborate more on your query.

Regards,

PS R

Former Member
0 Kudos

Thanks for your reply. The flags you indicated have been flagged as indicated in your screen shot.

Noticed that when i schedule the order next week which is also causing an overload i do get the dialogue box  for finite scheduling. Can i influence this so that it also shows up when i get an overload for oredrs planned this week and if so which profile should i adjust

thanks

Regards Bram de Waard

peter_atkin
Active Contributor
0 Kudos

Bram de Waard


In the Capacity Header screen of the work centre, which of the 3 check-boxes are active at the bottom of the screen?


PeteA