on 08-17-2016 4:48 AM
A job need to be running in my server continuously all the time. if it get cancelled it is a issue. so want some help is to is there any way to schedule the job in a way that if ever it get cancelled it will be re-triggered automatically.
Hi M.Ezzat,
Thanks for the DOC but I have already gone through that doc before and that is not related to us.
our job is like it works fine some time in history it has finished also. But sometime some time when we restart the server or due to ananomas issue it fails.
my requirement is that job should keep running if solman is up. this could not be periodic as I don't wont to stop it any time. to be restarted periodically.
Please suggest for any ideas.
Regards
Chetan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
maybe scheduling background job by triggering an event ?
Tables TBTCO / TBTCP can be used for checking the previous job status.
Regards,
Adrian
Hi Chetan,
At first try to go ahead with Ezzat's suggestion to find why job got failed from job logs. Then check with your functional team mates to put this job periodic so that if it fails once, it will be scheduled to run after the period mentioned during scheduling of job.
Regards,
Ashraf
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.