Skip to Content

Planned order dates not working with lead times in REM

Hi experts,

We are using REM manufacturing. we want planned order dates with lead time as below:

In house production time: 3 days

PIR date : 16.08.2016

Planned order date to be: 13.08.2016 as per client requirement.

I am using backward scheduling. I have tried as below

MRP run with parameter 1 3 1 3 2. i am getting result

Kindly suggest how can get result according lead time. or any other option to achieve results.

Best regards,

Santosh Sharma

Capture.PNG (17.4 kB)
Capture1.PNG (31.3 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Aug 16, 2016 at 12:12 PM

    Hello,

    Lead time scheduling will consider the operation time defined in routing and in basic date scheduling system will schedule the order as per the material master lead time and no capacity requirements will be generated.

    Please refer SAP help document,

    Calculating Production Dates (Lead Time Scheduling) - Planning Process - SAP Library

    and Basic dates and Lead time scheduling (MRP Param... | SCN



    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.