Hi experts,
We are using REM manufacturing. we want planned order dates with lead time as below:
In house production time: 3 days
PIR date : 16.08.2016
Planned order date to be: 13.08.2016 as per client requirement.
I am using backward scheduling. I have tried as below
MRP run with parameter 1 3 1 3 2. i am getting result
Kindly suggest how can get result according lead time. or any other option to achieve results.
Best regards,