HI all,
I just start to learn SAP Business One and encounter one bothering issue. Please kindly share with me your knowledge how to solve this issue.
scenario as below;
1. create one production order today, and release this order on the later day (for example 3 days later).
2. intend to issue material to production order today but it is not allowed, however, I can do this at the next day when I checked the next day. I doubt this is due to some date limitation.
Can anyone show me how this is controlled? or any document can explain all this.
thanks for help!
Linda
Dear Linda
Where do you come from? HK?
What's the production order status?
Do you have enough material for production?
Any error message?
Please capture the screen.
Regards
Edmund
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Edmund,
I have found the cause, it is due to the lead time setup in the item mater. After I setup reasonable lead time in my item master planning data I could issue the stock I need manually to production order. Which means I need to advise users maybe longer lead time number is needed if they want to manually issue stock to production order earlier than planning date.
do you have any other experience for sharing?
thanks very much!
regards,
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.