Independent Requirements and dependent requirements

Hi Gurus,

Which Production order status of independents requirement (PIR) will remove Dependent Reservation (OrdRes). PIR is Fert and OrdRes is generated for its SFG.

Teco to FERT PrdOrd is removing OrdRes for HALB in my system but is there any other status which can do the job other than Clsd, teco and DLFL which I found through research.


Thankyou

Shankar

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 15, 2016 at 07:12 PM

    Hi Shankar,

    I think you already mention all Prod Order Status relevant to clear the reservation.

    Just to add, when you do final confirmation, you can tick "Clear Reservation" to remove the dependant reservation of the components as well. But this is optional.


    The best way is to check the component in the Production Order, if it has "Deletion" or "Final Issue" indicator ticked, it means the reservation is closed.


    BR,

    Hengky

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 16, 2016 at 09:44 AM

    Hello,

    Run the report like RM06C020 in transaction code SE38 for the element you can see in the incorrect MD04 entry and check transaction code MD04 again. Sometimes, the inconsistency is only cleared when you run the report using the reservation number. Read SAP note 115899 carefully before you run the report.

    Also refer SAP note 2047547 - MD04, MD05: Dependent requirement without planned order

    Dependent incorrect requirements can be found and deleted using the attached report ZCHECKRESB1

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello,

      As I know it has nothing to do with rescheduling horizon. In production it is working because in production system you execute the confirmation and good issue with clear the reservation of your production orders. However in Development and Quality systems old production order may be pending for confirmations or final good issue to an orders. So you need to post the confirmation with clear open reservation or do TECO all production orders. You can revoke the TECO if required.

      Best Regards,

      R.Brahmankar

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.