Hello expoerts,

I have my application developed on the BI Platform, using SAP Design Studio 1.6 SP2 and I was not able to make a planning application work.

When I try to set the Planning Connection to a BW system on the Application properties, I only have the OLAP connections available in the drop down box., and I couldn´t make it work using an OLAp connection.

If I export the application and inport it and execute it on Local mode, assigning a BW system in the Planning Connection, it works fine.

Has anybody tried to use Integrated Planning on an application on the the BI Platform? Could you please help me on the steps to make it work?

Thank you very much,

Anderson

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 17, 2016 at 05:40 PM

    This message was moderated.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 22, 2016 at 03:14 PM

    Hi Anderson,

    could you post a screenshot of the settings you are talking about.

    I am here on a DS where planning works and I can not really see any special settings that need to be done for planning.

    regards

    Cornelia

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.