Morning,

Our actuals from ERP for PS reflects incorrectly on PPM Portal.

Our current Financial Year is from 26.03.16 to 25.03.17 , which is 2017

26.03.2016 to 25.04.2016 = Period 1

26.04.2016 to 25.05.2016 = Period 2

26.05.2016 to 25.06.2016 = Period 3

26.06.2016 to 25.07.2016 = Period 4

26.07.2016 to 25.08.2016 = Period 5

26.08.2016 to 25.09.2016 = Period 6

26.09.2016 to 25.10.2016 = Period 7

26.10.2016 to 25.11.2016 = Period 8

26.11.2016 to 25.12.2016 = Period 9

26.12.2016 to 25.01.2017 = Period 10

26.05.2016 to 25.02.2017 = Period 11

26.05.2016 to 25.03.2017 = Period 12

Issue:

If actuals were posted on 10.05.16, it moves it to the portal to Period 5 for 2016 instead of Period 2 for 2017.

Any suggestions on how to resolve this?

Annelize

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 16, 2016 at 03:59 AM

    Hi Aneelize,

    Please make sure that following global switch is enabled in PPM Customizing (SAP Portfolio and Project Management > Portfolio Management > Global Customizing > Global Settings > Override Default Global Settings)

    --> Area 0010 and sub-area 0007 - Fiscal year variant is set to the FY in ECC. For your case, I presume that is V3.

    Hope this helps.

    Best regards

    Aditya

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 16, 2016 at 02:47 AM

    Hi Annelize,

    How is your fiscal year variant configuration maintained in PPM? Is it same as ERP??

    Can you share screenshot of the same?

    Regards

    Sammar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 17, 2016 at 06:45 AM

    Hi Chatsworth,

    PPM 6.0, SAP NETWEAVER 7.4

    Annelize

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 18, 2016 at 12:43 PM

    Hi All,


    I logged an OSS a few days ago as well, and the recommendation came through last night to run /RPM/FICO_PLANNING_INT but only for Planning. It worked and all our financials are mapped correct now.


    Thank you so much for all your support and help!!


    Annelize

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.