Hi Experts,
I am using same work center for both FINISHED material and SEMI FINISHED material. After running MRP CM01 shows planned order distribution each day. For overloaded days I want to reschedule some of the planned orders in CM01 by changing the planned order date to less load days (using capacity details/period --> select planned order --> order header). Is that the correct method for Capacity levelling? I see that the planned orders created for FINISHED material are not editable-Shows message 'Planned order may not be changed'. Only those for the SEMI FINISHED material are only editable. Why this is so?
If I want to change the date of a planned order to a new date to level the capacity, which date I should change in MD12 because the planned order has all below dates
Thanks